How to Submit an Application for an Individual Wastewater or Stormwater Permit

How to submit an application for an individual permit or authorization – electronically or via hardcopy. Find information about and forms for public involvement, links for TCEQ’s secure file submittal, making payments, and checking on your application’s status.

Status of Stormwater and Wastewater Applications – Check on the status of a submitted application. 

Submitting an Application Online

You can ensure efficient processing of your application for a new, renewed, or amended individual wastewater permit by submitting your application online through STEERS.

If you apply via STEERS, additional copies (paper or electronic) are not required.

Submitting a Hardcopy

If you’re unable to submit an application online, you may submit it as a hard copy. For the application to be considered complete you must provide one completed physical application – an original signed and notarized paper copy – and one exact electronic copy of the application via our secure file transfer site  TCEQ Send [Texas Administrative Code, Title 30 (30 TAC), Section 305.48] 

Public Involvement Plan

All new and major amendment wastewater and stormwater individual permit applications must include a Public Involvement Plan (PIP) form. Individual permit applications are being updated with this new requirement.

The information you provide will help ensure public participation in the permitting process as indicated by your situation.

TCEQ Public Participation Plan GI-607 - TCEQ’s expectations for public involvement; ensuring Texans are notified, and that they can understand proposed decisions, provide input, and ask questions.

Plain Language Summary of Application

All new and amendment wastewater and stormwater permits must include a summary of the application that provides a clear understanding of key information for the public.

Summary Application Form and Instructions (TCEQ Form-20972)

Payment and Processing

ePay Online Payment System – Pay your application processing fee.

The initial review start date will begin once the original application is stamped received by the TCEQ mailroom.

When to Submit Your Application

Submit an application for a new or amended permit about a year before the anticipated construction date.

Submit an application to renew an existing permit 180 days before the permit expiration date. If you’re unable to meet that deadline, please send an email to:

Expired Permits

If your existing permit has expired, you cannot renew it. You must apply for a new permit.

Related Content

See our webpages related to each type of permit for detailed instructions and forms.

Tools for Completing Water Quality Applications – Links to state and federal websites with maps and other information you may need to complete an application.

Water Quality Permit Maintenance Forms – What to do after your permit has been issued.

Environmental Permitting: Participating in the Process – Find public meetings and hearings and locate information about pending permits.

Pending TCEQ Permits – Submit comments about a permit application.

Commissioners Integrated Database (CID) – Information about a specific permit action. For questions about the CID, contact the Office of Chief Clerk at chiefclk@tceq.texas.gov.