Types of Authorization for Turbines
Tells how to apply for a flexible or construction permit that covers turbines if not covered by a PBR or under the de minimis rule.
The following list of permit authorizations is arranged in order of the time and effort required to obtain authorization.
- Permits by Rule (PBRs) for Turbines. These links will take you to the specific PBR that may apply to your facility. Review the general information for qualifying and applying for a PBR. Contact air permitting staff regarding partial permitting policies.
- Standard Permit for Electric Generating Units. Certain engines used for the generation of electricity must use this standard permit instead of the PBR.
- Construction Permit
- If you cannot qualify for another type of permit authorization, you must apply for a case-by-case construction permit under 30 TAC Chapter 116.
Questions? We Can Help
If you have questions regarding this guidance please contact us.