Deadline to Renew Your Stormwater Construction General Permit Authorization

May 2023 – Currently permitted construction sites with ongoing activities need to renew their stormwater Construction General Permit (CGP) authorization by June 5, 2023, at 8:00 PM CST. Active construction sites that fail to renew by the deadline can receive a violation and potential fines.

For operators of ongoing large construction activities that disturb five or more acres, or are part of a common plan of development that disturbs five or more acres:

For operators of ongoing small construction activities that disturb at least one but less than five acres, or are part of a common plan of development that disturbs at least one but less than five acres:

  • Create, update, and implement your SWP3 to meet the 2023 CGP requirements.
  • Complete and post an updated Small Construction Site Notice form (TCEQ-20963).

Operators of small construction sites may also:

If you no longer need coverage under the CGP and you have reached final stabilization at the site, you must submit a Notice of Termination (NOT) in STEERS before your permit authorization expires on June 5, 2023.

Be sure to review a copy of the renewed 2023 TXR150000 CGP. 

For more information, visit our Assistance Tools for Construction Stormwater General Permits webpage. For questions, please call the SBLGA hotline at 800-447-2827.