Types of Authorization for Turbines

Describes which authorizations may be applicable to turbines.

The following list of permit authorizations is arranged in order of the time and effort required to obtain authorization.

  • Permits by Rule (PBRs) for Turbines. These links will take you to the specific PBR that may apply to your facility. Review the general information for qualifying and applying for a PBR. Contact air permitting staff regarding partial permitting policies.
    • Title 30, Texas Administrative Code, Section 106.511 - Portable and Emergency Engines and Turbines
    • Section 106.512 - Stationary Engines and Turbines
    • Note: 106.512 cannot be used for electric generators, use Standard Permit.
  • Standard Permit for Electric Generating Units. Certain engines used for the generation of electricity must use this standard permit instead of the PBR.
  • Construction Permit - If you cannot qualify for another type of permit authorization, you must apply for a case-by-case construction permit under 30 TAC Chapter 116.
    • Readily Available Permit – Certain simple cycle turbines may qualify for authorization through a Readily Available Permit.

Questions? We Can Help

If you have questions regarding this guidance, please contact us.